It is rare that a construction lawsuit raises multiple useful lessons for contractors in protecting their payment rights, but Wang Electric v. Smoke Tree Resort
did just that.
The 2012 Arizona Court of Appeals case, which was complicated and confusing even by a construction lawyer’s standards, can be summarized in part as follows:
Reasonable Time in Serving a Lien.
A mechanics’ lien
must be served within a reasonable time after it is filed. Surprisingly, in Wang Electric
the court considered a 90-day delay to be reasonable but cautioned that “reasonableness” should be determined on a case-by-case basis. Takeaway: Without clear time limits, a subcontractor filing a mechanics’ lien should serve copies on every appropriate party as soon after filing the lien as time permits.
Liens Against the Tenant and Owner.
When work is initiated by a tenant, a mechanics’ lien is effective against the property owner only if the tenant is an “agent” of the owner. In this case, the tenant was determined to be the owner’s agent, and the court ruled that service on one was the same as service on the other. Takeaway: Since agency relationships are not necessarily clear, whenever a situation calls for a mechanics’ lien, the lien claimant should serve the pre-lien on both the tenant and the owner and sort out the agency issues later.
Too Many Liens?
Subcontractors and suppliers are allowed to “cover their bases” by serving multiple pre-liens. Takeaway: When in doubt as to who to serve your pre-lien on, it is better to serve too many parties than too few.
Liens against Tenant Improvements.
A mechanics’ lien that is recorded solely against a tenant’s interest in tenant improvements can survive the lease’s termination under certain circumstances (discussed below). Takeaway: If you are filing a mechanics’ lien against a leasehold improvement, and your contract is with the tenant, you will want the tenant to be considered an “agent” of the owner. A common example of agency is that the tenant is making improvements at the direction of the owner.
Unjust Enrichment.
In case your lien fails, you might be able to make an unjust enrichment claim, but only if the owner did not pay the general contractor or engaged in “dishonest conduct” (more below). Takeaway: An unjust enrichment claim is hard to win, and it is no substitute for properly preserving and enforcing your mechanics’ lien rights.
BACKGROUND
This case involves leasehold improvements at a site that long-time Phoenicians will remember as Dale Anderson’s "The Other Place" restaurant at the Smoke Tree Resort on Lincoln Drive. In October 2007, the Smoke Tree leased the vacant restaurant space to REM on Lincoln. The lease required REM to remodel the space, and Smoke Tree agreed to reimburse REM for the first $840,000 in remodeling expenses.
REM hired KAI Designs to be the general contractor, and their contract called for REM to make monthly progress payments to KAI. KAI then directly subcontracted with Wang Electric, Aero Automatic Sprinkler Co., Beecroft LLC, Adobe Paint, Adobe Drywall and other subcontractors.
Even though REM’s contract with Smoke Tree called for REM (the tenant) to pay KAI (the general), and for Smoke Tree (the owner) to reimburse REM, Smoke Tree paid the first $790,000 in construction costs directly to KAI.
In April 2008, the progress payments stopped, and unpaid subcontractors filed mechanics’ liens on Smoke Tree’s property and/or REM’s leasehold interest. Next, subcontractors filed lawsuits against Smoke Tree, REM, KAI and, in some cases, other subcontractors. All six subcontractors sought damages for breach of contract (against the general), sought to foreclose their mechanics’ liens (against the owner and tenant) and, as a Plan B, claimed that the owner and tenant had been unjustly enriched.
The waters were further muddied by the fact that, at some point during the controversy, REM’s lease was terminated, exposing the owner to claims that otherwise would have been focused on the tenant.
The ensuing flurry of claims, cross-claims, motions for summary judgment, etc., defies discussion in this simple article. However, while much of the Court of Appeals’ opinion in this case is devoted to thorny legal questions, the judges did raise some issues that have practical day-to-day importance to owners, contractors, subcontractors and suppliers.
Serving a Mechanics’ Lien on the Owner.
Arizona law requires that a copy of a mechanics’ lien be served on a property owner within a reasonable time after filing. Unfortunately, the statute doesn’t define “reasonable time.” In Wang Electric, a mechanics’ lien was served on the owner three months after it was filed, and only as an attachment to a complaint.
In response to the owner’s argument that three months was unreasonably long, the Court of Appeals ruled that, in this case, 90 days was not unreasonable but offered no standard for future notifications, stating that reasonableness should be determined on a case-by-case basis.
As a practical matter, subcontractors should disregard the 90-day lag period that the court allowed here. Rather, in the absence of clear time limits, a subcontractor filing a mechanics’ lien should serve copies on every appropriate party as soon after filing the lien as time permits.
Preliminary 20-Day Notice Requirements.
As a general rule, on commercial projects it is wise to serve a preliminary 20-day notice (or “pre-lien”) on all responsible parties, including the property owner or the owner’s agent.
However, when work is initiated by a tenant, a mechanics’ lien typically attaches only to the leasehold interest and tenant improvements. The property itself is subject to the lien only if the tenant is found to be an “agent” of the owner. Since agency relationships are not always clear, it is a good practice to serve the pre-lien on both the tenant and the owner.
In Wang Electric,
the owner (Smoke Tree) argued that a mechanics’ lien was invalid because the subcontractor served a pre-lien on the tenant (REM) but not on the owner directly. The court ruled that, in this case, the tenant was an agent of the owner because the lease required the tenant to extensively remodel the property in accordance with plans and specifications approved by the owner. Thus, for lien purposes, service upon the tenant was the same as service upon the owner.
On a related issue, the owner challenged another mechanics’ lien on the grounds that the subcontractor sent too many pre-liens. The sub had sent three pre-liens – to the owner, to the tenant, and to an agent of the two parties. The court rejected the owner’s challenge, noting that “a Laborer may ‘cover its bases’ by serving multiple preliminary 20-day lien notices naming different owners and reputed owners as long as such service is timely.” The moral is, when in doubt as to who to serve your pre-lien on, better to serve too many parties than too few.
Mechanics’ Liens Against a Terminated Leasehold Interest.
When a commercial tenant contracts for construction work, it creates a complicated situation with respect to the mechanics’ lien. As mentioned earlier, the termination of REM’s lease exposed Smoke Tree to claims that normally would have been aimed at the tenant.
In Wang Electric,
all of the subcontractors except one had lien rights against the owner’s interest because the tenant was ruled to be an “agent” of the owner. The exception, Adobe Drywall, had lien rights only against the leasehold estate. That became a problem when the tenant’s lease was terminated.
Adobe Drywall argued that, despite the lease termination, it still had a right to claim a lien against the improvements that REM left behind. The court found that a mechanics’ lien, recorded solely against a tenant’s interest in improvements made to a leased property, will survive the lease’s termination if:
| Lang Thal King & Hanson PC
Lang Thal King & Hanson PC is a 2024 Best Law Firms Metro Tier 1 (Scottsdale) selectee for Construction Law, Construction Litigation and Commercial Litigation, and a Tier 2 selectee for Arbitration.
The act of visiting or communicating with Lang Thal King & Hanson PC, via this website or by email does not create an attorney-client relationship. Communications from non-clients are not subject to client confidentiality or attorney-client privilege.
Further, the articles, discussion, commentary, forms and sample documentation contained in this website are offered as general guidance only and are not to be relied upon as specific legal advice. For legal advice on a specific matter, please consult with an attorney who is knowledgeable and experienced in that area. While the articles on this website accurately describe applicable law on the subject covered as of the date of publication, the law continues to develop with the passage of time. Accordingly, care should be taken to verify that the statutes, case law and regulations described have not changed since the article's publication.
The lawyers listed in this website practice law only in the jurisdictions where they are admitted. This website is regulated by the Arizona Rules of Professional Conduct.
Lang Thal King & Hanson construction, litigation and business attorneys represent contractors, subcontractors and general business owners in construction law, contractor licensing, collections and general commercial litigation in the Phoenix area and throughout Arizona.