In comparison to mechanics’ and materialmen’s liens, the steps required to preserve the right to sue on a public works payment bond are fewer; however, they are critical. If you miss a deadline, you forfeit your right to payment from the surety. Therefore, note the date of each step on the worksheet, and calendar the next deadlines to preserve your rights as beneficiary on the bond.
The Arizona law relating to contractor claims on public buildings and improvements (A.R.S. §§ 34-222 et seq.) is known as the “Little Miller Act.” It is patterned after and generally consistent with the federal Miller Act, which governs contractor claims on federal buildings and improvements.
Send the general contractor a written request for the information you will need for your Preliminary 20-Day Notice and for information on the project payment bond.
See Form A, "Written Request to Owner for Information for Preliminary 20-Day Notice," available in PDF and edit-ready Word formats
A.R.S. § 33-992.01(B) requires service of the written Preliminary 20-Day Notice of lien to: (a) the owner or reputed owner, (b) the original contractor or reputed contractor, (c) the construction lender or reputed construction lender, and (d) the person with whom he contracts.
See Form B (Part 1), "Preliminary 20-Day Lien Notice" (PDF • Word)
Send a copy of the Preliminary 20-Day Notice to the payment bond surety as well. In fact, the bond itself may require you to serve the surety. When you receive a copy of the payment bond, review it carefully to make certain that you understand all the conditions for payment.
Prepare the Preliminary 20-Day Notice and serve it in the same manner as described in the discussion of mechanics' liens, by either first-class mail with a certificate of mailing, registered mail, or certified mail, postage prepaid, and addressed to the business or residence of the party served.
You must be able to prove that you served the Preliminary 20-Day Notice. The notice form contains an "acknowledgment of receipt." In the event you do not receive the acknowledgments within thirty days, however, prepare an affidavit of service stating the time, place and manner of service. It’s a good idea to prepare the affidavit of service at the same time you serve the Preliminary 20-Day Notice, while the information is fresh.
See Form C, "Affidavit of Service" (PDF • Word)
Note that the certificate of mailing or mail receipt must be attached to the affidavit (A.R.S. § 33-992.02). Keep the affidavit in a safe place with a copy of the Notice and the U. S. Postal Service certificate of mailing or delivery receipt.
When the value of the labor or materials you provide exceeds the 20-Day Notice amount by 20% or more, you must serve a supplemental 20-Day Notice.
The initial Preliminary 20-Day Notice will protect your lien rights only up to 120% of the amount stated in the notice. If the value of your labor or services exceeds the amount stated by more than 20%, you must prepare and serve a supplemental Preliminary 20-Day Notice within 20 days. Serve the supplemental notice in the same way that you served the initial 20-Day Notice (see Steps 2 and 3 above).
This date is critical because it determines the deadlines for the 90-day notice and for filing a lawsuit on the bond. Work done solely to effect repairs, make corrections, or complete a final inspection does not qualify as work on the original contract and will not extend the deadline. Make certain that you have completely performed your contract, and record the date when you complete performance. Then calculate the 90-day deadline for serving your 90-day notice.
Subcontractors and material suppliers covered by the Miller Act who do not have a contract directly with the general contractor must give a 90-day notice within 90 days after performing work or providing materials under their original contract.
See Form E, "90-Day Notice for Bonded Public Works" (PDF • Word)
Note that work done solely to make repairs or corrections or to complete a final inspection does not qualify as work on the original contract, and it will not extend the deadline. Keep good evidence, such as time sheets, superintendent's log, and photos of your last day of work.
Serve the notice in the same manner as provided for 20-day preliminary notices (see Step 3 above) by either first-class mail with a certificate of mailing from the U.S. Postal Service, registered mail, or certified mail, postage prepaid, and addressed to the business or residence of the party served.
The time for filing a lawsuit on the payment bond expires one year after the last day on which you perform work under your contract, as described in Step 5 above. If you are an early provider on the project, this deadline may arrive before the project closes and retention monies become due.
| Lang Thal King & Hanson PC
Lang Thal King & Hanson PC is a 2024 Best Law Firms Metro Tier 1 (Scottsdale) selectee for Construction Law, Construction Litigation and Commercial Litigation, and a Tier 2 selectee for Arbitration.
The act of visiting or communicating with Lang Thal King & Hanson PC, via this website or by email does not create an attorney-client relationship. Communications from non-clients are not subject to client confidentiality or attorney-client privilege.
Further, the articles, discussion, commentary, forms and sample documentation contained in this website are offered as general guidance only and are not to be relied upon as specific legal advice. For legal advice on a specific matter, please consult with an attorney who is knowledgeable and experienced in that area. While the articles on this website accurately describe applicable law on the subject covered as of the date of publication, the law continues to develop with the passage of time. Accordingly, care should be taken to verify that the statutes, case law and regulations described have not changed since the article's publication.
The lawyers listed in this website practice law only in the jurisdictions where they are admitted. This website is regulated by the Arizona Rules of Professional Conduct.
Lang Thal King & Hanson construction, litigation and business attorneys represent contractors, subcontractors and general business owners in construction law, contractor licensing, collections and general commercial litigation in the Phoenix area and throughout Arizona.